86th Street Multi-Modal Traffic Study
Recently the City of Bloomington was awarded federal grant money as part of the Efficiency and
Energy Conservation Block Grant (EECBG). One of the projects selected for completion with this
grant money was the 86th Street Multi Modal Traffic Study.
This study will develop a preliminary design for balancing vehicles, pedestrian and bicycle
needs for the 86th Street corridor from Xerxes Avenue to East Old Shakopee Road. This corridor
was identified in the Alternative Transportation Plan (ATP), dated July 7, 2008, as a primary
east-west corridor in the City for bike and pedestrian activity. The corridor will provide a
connection to trails and destinations such as city parks, regional park connections, schools,
commercial and employment areas including the Mall of America, and bus routes.
The project was awarded to SRF Consulting on October 26, 2009 and the kick-off meeting was held
on October 30, 2009.
The study will make use of a Stakeholders Group to meet regularly and provide feedback from
numerous perspectives about the project and the proposed options. I have included information about
the role of the Stakeholders Group as well as a list of the group members.
-
Project schedule (26KB PDF)
-
Stakeholder description (17KB PDF)
-
Stakeholder group (15KB PDF)
-
Central and East segments open house documents - March 2010
Open house was held March 29, 2010
-
New Approved Changes
-
Interim Recommendation (Council approved 6/7/10)
The interim recommendations will be implemented along with the planned
maintenance (seal coat) project this summer. The City of Bloomington will
be converting the striping on the corridor from the existing 4-lane
configuration (2-lanes in each direction) to a 3-lane configuration (1-lane
in each direction with a continuous dual left-turn lane, and a bike route
on each side). The change will not affect the intersection of Lyndale
Avenue, where the bike route will end and there will be a "Share the Road"
section as you approach this intersection from both sides. Some signal
modifications will be needed at the Nicollet, Portland, 12th Avenue and
Cedar intersections.
-
Long Term Recommendation (Council approved 6/7/10)
The long term changes that were approved for 86th Street will include
constructed improvements at Lyndale Avenue to continue the route through
this intersection (for bike route continuity), and to construct the
intersection improvements at Nicollet Avenue (for long term level of
service improvements) and Portland Avenue (for safety improvements).
-
West segment open house documents - December 2009
Council approved options options, January 25, 2010
-
Xerxes Avenue to Penn Avenue
-
Penn Avenue to I-35W
For more information, contact:
Paul Jarvis
Traffic Management Coordinator
1700 W 98th Street
PH: 952-563-4548, FAX: 952-563-4868
Email: pjarvis@ci.bloomington.mn.us
|