Project updates

Safe Routes to School Project

The updates listed below refer to the Safe Routes to School project. To find updates regarding other projects, go to major road construction projects.

October 2011

October 13, 2011
  • East 88th Street area
    East 88th Street from Park Avenue to 14th Avenue


    Sod and tree installation is complete. Punch list work remains.
  • 3rd Avenue area
    3rd Avenue from East 91st Street to East 92nd Street


    Sod and tree installation is complete. Punch list work remains.
October 7, 2011
  • East 88th Street area
    East 88th Street from Park Avenue to 14th Avenue


    Paving of bituminous driveways is complete. Sod and tree installation is anticipated to complete by the end of the day Friday, October 7.
  • 3rd Avenue area
    3rd Avenue from East 91st Street to East 92nd Street


    Paving of bituminous driveways is complete. Sod and tree installation has started and is anticipated to complete early the week of October 10.
  • Morris Avenue area
    Morris Avenue from West 85th Street to 90' north of Morris Circle

    Sod/seed and tree installation is complete. Punch list work remains.

September 2011

September 30, 2011
  • East 88th Street area
    East 88th Street from Park Avenue to 14th Avenue


    Concrete work is complete. Paving of bituminous driveways is scheduled for the week of October 3. Boulevard restoration has started and will continue the week of October 3. Sod and tree installation is scheduled for the week of October 3.
  • 3rd Avenue area
    3rd Avenue from East 91st Street to East 92nd Street


    Concrete work is complete. Paving of bituminous driveways is scheduled for the week of October 3. Boulevard restoration has started and will continue the week of October 3. Sod and tree installation is scheduled for the week of October 3.
  • Morris Avenue area
    Morris Avenue from West 85th Street to 90' north of Morris Circle

    Hydrant relocation is complete. Concrete work is complete. Boulevard restoration has started and will continue the week of October 3. Sod and tree installation is scheduled for the week of October 3.
September 23, 2011
  • East 88th Street area
    East 88th Street from Park Avenue to 14th Avenue


    Tree removal is complete in the area. Concrete work has started in the area and will complete the week of September 26. Paving of bituminous driveways is scheduled for the week of September 26 with boulevard restoration to follow. Tree installation is anticipated to begin late in the week of September 26 or the week of October 3.
  • 3rd Avenue area
    3rd Avenue from East 91st Street to East 92nd Street


    Grading for sidewalk installation is complete. Concrete work has started in the area and will continue the week of September 26. Paving of bituminous driveways is scheduled for late in the week of September 26 or the week of October 3 with boulevard restoration to follow. Tree installation is anticipated to begin late in the week of September 26 or the week of October 3.
  • Morris Avenue area
    Morris Avenue from West 85th Street to 90' north of Morris Circle

    Grading for sidewalk installation has started and will complete the week of September 26. Hydrant relocation at the corner of W 85th St/Morris Avenue is anticipated to complete by the end of the day Friday, September 23 in preparation for sidewalk installation. Concrete work is scheduled for the week of September 26. Boulevard restoration and tree installation is anticipated to occur the week of October 3.
September 16, 2011

A pre construction conference was held on Wednesday, September 7.

  • East 88th Street area
    East 88th Street from Park Avenue to 14th Avenue


    Tree removal has started in the area and will complete the week of September 19. The contractor has started removals, excavation and grading for sidewalk installation and will continue the week of September 19. Concrete work is scheduled to begin the week of September 19.
  • 3rd Avenue area
    3rd Avenue from East 91st Street to East 92nd Street


    Tree removal in the area is complete. The contractor anticipates beginning removals, excavation and grading for sidewalk installation late in the week of September 19.
  • Morris Avenue area
    Morris Avenue from West 85th Street to 90' north of Morris Circle

    Tree removal in the area is complete.
September 9, 2011

A pre construction conference was held on Wednesday, September 7.

  • East 88th Street area
    East 88th Street from Park Avenue to 14th Avenue


    Tree removal is scheduled in this area for early in the week of September 12. The contractor plans to begin removals, sidewalk excavation and concrete installation in this area the week of September 12.
  • 3rd Avenue area
    3rd Avenue from East 91st Street to East 92nd Street


    Tree removal is scheduled in this area for early in the week of September 12.
  • Morris Avenue area
    Morris Avenue from West 85th Street to 90' north of Morris Circle

    Tree removal is scheduled in this area for early in the week of September 12.
September 6, 2011

A pre construction conference is scheduled for Wednesday, September 7. Construction is anticipated to begin the week of September 12.

 

August 2011

August 26, 2011

Construction is anticipated to begin in early-mid September.

August 19, 2011

The contract was awarded at the regular council meeting on Monday, August 15. Construction is anticipated to begin in early-mid September.

August 12, 2011

The bid opening for this project was held Tuesday, August 9 and is proposed for Award of Contract at the next regular Council meeting on Monday, August 15.

 

For more information, contact:

Bob Simons, Civil Engineer
1700 W. 98th Street
PH: 952-563-8758, FAX: 952-563-4868
E-mail: bsimons@ci.bloomington.mn.us